Present: Yannick, Patrick, Mathias M., Emmanuel, Gregory, Henry Joy, Fred, Mathias S. (partly).

Emmanuel's summary document

MEGACAM T05 operations
-  Yannick explains that there were two problems with the first batch of test data sent by Jean-Charles: (1) the fringe pattern did not correspond to the new flats and (2) The photometric calibration fields used for the grid may not have been reduced with the correct flatfields.
-  Henry Joy will try to understand better the problem with his completeness script. He will try to come up with a solution before the end of February.

WIRCAM PI processing

-  There is not yet an explanation to the photometric shifts in Ks.
-  Mathias will explain to Henry how to use Pickles to calibrate the Bracket Gamma images during the next week.

T05 developments

-  Gregory will write a cronjob that checks that the condor tasks are active, and sends a warning e-mail in case of missing tasks (deadline: end of February).
-  Gregory will bring back the "quality" parameters into the main image table. Deadline: end of this week. Update: done.
-  Emmanuel proposes to regroup the flats and masks by instrument. Two "path" fields must be added to the instrument table, and a specific directory browser must be added to the interface. Deadline: end of next week. Update: Gregory has added the path fields.
-  Gregory will check that the pre-ingestion of QSO status tables works correctly through NFS.

System/hardware

-  Fred will perform an upgrade of Condor. Proposed deadline: end of this week.
-  Apparently e-mails are correctly sent by dotproject.
-  Fred prefers to wait for a new release of PHPMyBB to fix the login problem.